[WG: Sakai QA] Sakai 11 proposed schedule

[sakai-dev, sakai-qa, sakai-pmc (at new apereo.org address)]

Hi All,

On Tuesday, we held a special meeting of the Sakai Core team [1]. The "special" part was to hold it at a time other than our usual Thursday at 10 am Eastern so that others might have a chance to attend, who normally cannot make that time.

Based on the discussion we came up with the following schedule [2]. Questions, comments, suggestions, and concerns are all welcome.

2015 April 14 Testing iFrame using Complex tools
2015 May 1 ReflectUtils and Java 8 in trunk
2015 May 11 Morpheus complete
2015 June 5 Identify Scope
2015 June 22 String freeze and cut Sakai 11 branch in Github
2015 August Shift focus to Bug Bashes/ QA
2015 October Release candidate 01
2015 December GA (production release)

This is just a draft. It is based on the current state of Sakai, which includes that Morpheus (responsive design) is in trunk, as is Dashboard, and that we are planning to have in the Gradebook Enhancement Project, and the Lessons Enhancement Project, and hoping, and likely, to get in some additional Samigo (Test and Quizzes) updates (already a number of updates in trunk).  We also anticipate some further evolution of Morpheus over the next month or two. 

A couple of notes:
* This schedule provides us the opportunity to use Open Apereo to put the final touches on Sakai 11 scope, perhaps doing some additional improvements.

* We plan to test the week of April 14, the week after next. Not a full Morphues test, but testing "inlining", the changes that have been made to the portal, and undoubtedly could hit some Morphues issues.

* We whether it might be better to branch Sakai 11 later. 

* We want to move to Java 8. Java 7 has reached end of life.

* We need to refine our dates a little more from August and later.

* Releasing in the holiday timeframe, December, has significant schedule risk. 




Thanks,
Neal Caidin
Sakai Community Coordinator




_______________________________________________
sakai-qa mailing list
[hidden email]
http://collab.sakaiproject.org/mailman/listinfo/sakai-qa

TO UNSUBSCRIBE: send email to [hidden email] with a subject of "unsubscribe"
Neal Caidin-3 Neal Caidin-3
Reply | Threaded
Open this post in threaded view
|

Re: [WG: Sakai QA] [Building Sakai] Sakai 11 proposed schedule

I think so. 

Right now, scope definition cutoff is June 5, which means we would need to hear about your feature on this Jira


For tracking.

We might want to be a little more explicit.


On Thu, Apr 2, 2015 at 8:50 AM, Adam Marshall <[hidden email]> wrote:

Is June 22 that “feature freeze” cut-off point? Hopefully Adrian Fish & Flying Kite will have finished merging our enhancements by then.

 

adam

 

--

 

** Note change of email address to [hidden email] **

 

Dr A C Marshall, WebLearn Service Manager, University of Oxford.

IT Services, 13 Banbury Rd, Oxford. OX2 6NN.

 

 

From: [hidden email] [mailto:[hidden email]] On Behalf Of Neal Caidin
Sent: 02 April 2015 13:32
To: Sakai-Dev; [hidden email] QA; [hidden email]
Subject: [Building Sakai] Sakai 11 proposed schedule

 

[sakai-dev, sakai-qa, sakai-pmc (at new apereo.org address)]

 

Hi All,

 

On Tuesday, we held a special meeting of the Sakai Core team [1]. The "special" part was to hold it at a time other than our usual Thursday at 10 am Eastern so that others might have a chance to attend, who normally cannot make that time.

 

Based on the discussion we came up with the following schedule [2]. Questions, comments, suggestions, and concerns are all welcome.

 

2015 April 14  Testing iFrame using Complex tools

2015 May 1 ReflectUtils and Java 8 in trunk

2015 May 11   Morpheus complete

2015 June 5     Identify Scope

2015 June 22   String freeze and cut Sakai 11 branch in Github

2015 August   Shift focus to Bug Bashes/ QA

2015 October  Release candidate 01

2015 December           GA (production release)

 

This is just a draft. It is based on the current state of Sakai, which includes that Morpheus (responsive design) is in trunk, as is Dashboard, and that we are planning to have in the Gradebook Enhancement Project, and the Lessons Enhancement Project, and hoping, and likely, to get in some additional Samigo (Test and Quizzes) updates (already a number of updates in trunk).  We also anticipate some further evolution of Morpheus over the next month or two. 

 

A couple of notes:

* This schedule provides us the opportunity to use Open Apereo to put the final touches on Sakai 11 scope, perhaps doing some additional improvements.

 

* We plan to test the week of April 14, the week after next. Not a full Morphues test, but testing "inlining", the changes that have been made to the portal, and undoubtedly could hit some Morphues issues.

 

* We whether it might be better to branch Sakai 11 later. 

 

* We want to move to Java 8. Java 7 has reached end of life.

 

* We need to refine our dates a little more from August and later.

 

* Releasing in the holiday timeframe, December, has significant schedule risk. 

 

 

[1] Sakai core team notes - http://etherpad.ctools.org/p/rmmt-2015-03-31

 

 

Thanks,

Neal Caidin

Sakai Community Coordinator

 

 

 



_______________________________________________
sakai-qa mailing list
[hidden email]
http://collab.sakaiproject.org/mailman/listinfo/sakai-qa

TO UNSUBSCRIBE: send email to [hidden email] with a subject of "unsubscribe"
Dr. Chuck Dr. Chuck
Reply | Threaded
Open this post in threaded view
|

Re: [WG: Sakai QA] [Building Sakai] Sakai 11 proposed schedule

In reply to this post by Neal Caidin-3
Adam,

A key to this schedule is that the branch for 11 happens after the Apereo conference - so we can make final adjustments in Baltimore based on where things are at at that point.

/Chuck

On Apr 2, 2015, at 8:50 AM, Adam Marshall <[hidden email]> wrote:

Is June 22 that “feature freeze” cut-off point? Hopefully Adrian Fish & Flying Kite will have finished merging our enhancements by then.
 
adam
 
--
 
** Note change of email address to [hidden email] **
 
Dr A C Marshall, WebLearn Service Manager, University of Oxford.
IT Services, 13 Banbury Rd, Oxford. OX2 6NN.
 
 
From: [hidden email] [[hidden email]] On Behalf Of Neal Caidin
Sent: 02 April 2015 13:32
To: Sakai-Dev; [hidden email] QA; [hidden email]
Subject: [Building Sakai] Sakai 11 proposed schedule
 
[sakai-dev, sakai-qa, sakai-pmc (at new apereo.org address)]
 
Hi All,
 
On Tuesday, we held a special meeting of the Sakai Core team [1]. The "special" part was to hold it at a time other than our usual Thursday at 10 am Eastern so that others might have a chance to attend, who normally cannot make that time.
 
Based on the discussion we came up with the following schedule [2]. Questions, comments, suggestions, and concerns are all welcome.
 
2015 April 14  Testing iFrame using Complex tools
2015 May 1 ReflectUtils and Java 8 in trunk
2015 May 11   Morpheus complete
2015 June 5     Identify Scope
2015 June 22   String freeze and cut Sakai 11 branch in Github
2015 August   Shift focus to Bug Bashes/ QA
2015 October  Release candidate 01
2015 December           GA (production release)
 
This is just a draft. It is based on the current state of Sakai, which includes that Morpheus (responsive design) is in trunk, as is Dashboard, and that we are planning to have in the Gradebook Enhancement Project, and the Lessons Enhancement Project, and hoping, and likely, to get in some additional Samigo (Test and Quizzes) updates (already a number of updates in trunk).  We also anticipate some further evolution of Morpheus over the next month or two. 
 
A couple of notes:
* This schedule provides us the opportunity to use Open Apereo to put the final touches on Sakai 11 scope, perhaps doing some additional improvements.
 
* We plan to test the week of April 14, the week after next. Not a full Morphues test, but testing "inlining", the changes that have been made to the portal, and undoubtedly could hit some Morphues issues.
 
* We whether it might be better to branch Sakai 11 later. 
 
* We want to move to Java 8. Java 7 has reached end of life.
 
* We need to refine our dates a little more from August and later.
 
* Releasing in the holiday timeframe, December, has significant schedule risk. 
 
 
 
 
Thanks,
Neal Caidin
Sakai Community Coordinator
 
 
 
_______________________________________________
sakai-dev mailing list
[hidden email]
http://collab.sakaiproject.org/mailman/listinfo/sakai-dev

TO UNSUBSCRIBE: send email to [hidden email] with a subject of "unsubscribe"


_______________________________________________
sakai-qa mailing list
[hidden email]
http://collab.sakaiproject.org/mailman/listinfo/sakai-qa

TO UNSUBSCRIBE: send email to [hidden email] with a subject of "unsubscribe"
Neal Caidin-3 Neal Caidin-3
Reply | Threaded
Open this post in threaded view
|

Re: [WG: Sakai QA] [Building Sakai] Sakai 11 proposed schedule

Curious if there are any more suggestions or concerns about the schedule?

One question I received is what if a feature has already been added into trunk? The answer is that it will be part of Sakai 11, please make sure that it has a  Fix Version of Sakai 11 so that we can track it. It would not need to be added to the Jira tracking scope (features that are being proposed to get into Sakai 11) [1].

[1] Feature requests needing consideration for Sakai 11 -  https://jira.sakaiproject.org/browse/SAK-29008

Thanks,
Neal


On Fri, Apr 3, 2015 at 5:40 PM, Charles Severance <[hidden email]> wrote:
Adam,

A key to this schedule is that the branch for 11 happens after the Apereo conference - so we can make final adjustments in Baltimore based on where things are at at that point.

/Chuck

On Apr 2, 2015, at 8:50 AM, Adam Marshall <[hidden email]> wrote:

Is June 22 that “feature freeze” cut-off point? Hopefully Adrian Fish & Flying Kite will have finished merging our enhancements by then.
 
adam
 
--
 
** Note change of email address to [hidden email] **
 
Dr A C Marshall, WebLearn Service Manager, University of Oxford.
IT Services, 13 Banbury Rd, Oxford. OX2 6NN.
 
 
From: [hidden email] [[hidden email]] On Behalf Of Neal Caidin
Sent: 02 April 2015 13:32
To: Sakai-Dev; [hidden email] QA; [hidden email]
Subject: [Building Sakai] Sakai 11 proposed schedule
 
[sakai-dev, sakai-qa, sakai-pmc (at new apereo.org address)]
 
Hi All,
 
On Tuesday, we held a special meeting of the Sakai Core team [1]. The "special" part was to hold it at a time other than our usual Thursday at 10 am Eastern so that others might have a chance to attend, who normally cannot make that time.
 
Based on the discussion we came up with the following schedule [2]. Questions, comments, suggestions, and concerns are all welcome.
 
2015 April 14  Testing iFrame using Complex tools
2015 May 1 ReflectUtils and Java 8 in trunk
2015 May 11   Morpheus complete
2015 June 5     Identify Scope
2015 June 22   String freeze and cut Sakai 11 branch in Github
2015 August   Shift focus to Bug Bashes/ QA
2015 October  Release candidate 01
2015 December           GA (production release)
 
This is just a draft. It is based on the current state of Sakai, which includes that Morpheus (responsive design) is in trunk, as is Dashboard, and that we are planning to have in the Gradebook Enhancement Project, and the Lessons Enhancement Project, and hoping, and likely, to get in some additional Samigo (Test and Quizzes) updates (already a number of updates in trunk).  We also anticipate some further evolution of Morpheus over the next month or two. 
 
A couple of notes:
* This schedule provides us the opportunity to use Open Apereo to put the final touches on Sakai 11 scope, perhaps doing some additional improvements.
 
* We plan to test the week of April 14, the week after next. Not a full Morphues test, but testing "inlining", the changes that have been made to the portal, and undoubtedly could hit some Morphues issues.
 
* We whether it might be better to branch Sakai 11 later. 
 
* We want to move to Java 8. Java 7 has reached end of life.
 
* We need to refine our dates a little more from August and later.
 
* Releasing in the holiday timeframe, December, has significant schedule risk. 
 
 
 
 
Thanks,
Neal Caidin
Sakai Community Coordinator
 
 
 
_______________________________________________
sakai-dev mailing list
[hidden email]
http://collab.sakaiproject.org/mailman/listinfo/sakai-dev

TO UNSUBSCRIBE: send email to [hidden email] with a subject of "unsubscribe"



_______________________________________________
sakai-qa mailing list
[hidden email]
http://collab.sakaiproject.org/mailman/listinfo/sakai-qa

TO UNSUBSCRIBE: send email to [hidden email] with a subject of "unsubscribe"